Fact check: Kibera’s Zone B houses were due to be finished in January and lived in by May. Has that happened?

Listen to this article2 min listenAI voice
Tap play to hear this story

The promise: In May 2025, during registration of Kibera residents, Eastleigh Voice reported that Soweto East Zone B would be finished by January 2026 and that people would move in by May 2026.

Verdict: Not met. Both dates have passed, and no handover has been reported.

What we checked

  • 28 April 2026: at President Ruto’s site inspection, the Sh7.4 billion project was reported as more than 80% complete, according to The Star, Citizen Digital and The Standard.
  • 17 September 2026: the Boma Yangu project page still lists Zone B as “Ongoing”.
  • Keys: KNN found no report of any family receiving a Zone B house.
  • New date: KNN found no revised completion date.

Why it matters

Families in Zones C and D were given 13 days’ notice to leave in April so the next phase could start (KNN report). They were told they would be first in line for these houses.

If you have received a Zone B house or an allocation letter, KNN wants to hear from you: WhatsApp +254 721 319 377.

Sources: Eastleigh Voice, The Star, Citizen Digital, The Standard, Boma Yangu

No water? No power? Report it, then tell KNN.
KNN Newsroom
KNN Newsroomhttps://kibranewsnetwork.co.ke
KNN Newsroom is the staff byline for stories written, rewritten and edited at the Kibra News Network desk. Where a story credits an outside outlet, the original source is linked at the foot of the piece.
RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -
2027 is closer than it looks. Check that you are on the voters’ roll.

Most Popular

Recent Comments